ACCEPTANCE OF SUBSTANTIAL COMPLETION FOR THE SARASOTA HIGH SCHOOL - HISTORIC BUILDING RENOVATION PROJECT: PHASE I

Description

The architect has prepared the Certificate of Substantial Completion and the final punch list.  The project is substantially complete in accordance with the contract documents.  A copy of the final punch list is available for review at the Construction Services Department.



Recommendation
That the work performed by Willis A. Smith Construction, Inc. for the Sarasota High School - Historic Building Renovation project: Phase I, be accepted as substantially complete as of 5/20/2008.

Contact
LEMPE & COLLINS

Financial Impact
N/A


Attachment:  BAIenc6-17-08SHS-HistoricBldgRenovPh1SC.pdf